Utilities
An unexpected structural issue at a wastewater pumping station in Glasgow prompted the need for an accelerated infrastructure upgrade.
A large colony of ants had undermined the concrete plinth supporting the electrical control kiosk, leaving the structure unstable and presenting a safety concern.
With the pumping station located within a car park used by local residents and businesses, the project also required careful planning to minimise disruption.
TEXO was engaged to deliver a coordinated programme of electrical and civil engineering works, bringing forward a planned upgrade of the wastewater asset.
The scope included:
TEXO also liaised directly with local residents and businesses to agree suitable access arrangements and communicate planned works, ensuring the project could progress with disruption carefully managed.
The wastewater pumping station upgrade was successfully completed over a two-month period, safely, on time and within budget.
The project addressed the original structural safety concern while delivering the planned electrical infrastructure improvements.
Through coordinated project delivery and effective communication, TEXO demonstrated its capability to respond to unexpected challenges and deliver essential wastewater infrastructure upgrades.